Skip to content

Over the years, we’ve built parking structures that employed different structural framing methods. The system chosen depended on a variety of factors including land/site constraints, design functionality and accessibility of local resources.

Cost is a variable of all of the above. At times, the value of the land exceeds the price to add vertical to a project, similar to underground retention. Our experience has shown that each method has its own characteristics that can make it the correct application for a particular project.

7-12-13 Composite slab on metal deck

1. STRUCTURAL STEEL AND COMPOSITE SLAB ON DECK STRUCTURE 

  • Form work is minimal.
  • There is no leveling or topping slab required.
  • Floor flatness and levelness can be a challenge. Due to overload on decking formwork, super-flat floor requirements may be unattainable.
  • For safety concerns, work that can be completed underneath unfinished floors can be minimal.
  • Occupancy requires thermal insulation between non-conditioned space below. This can be accomplished by spray-on application.
  • Fireproofing of steel members is required. 
  • In the long term, painting of surfaces can become a maintenance expense.

Post tensioned

 

2. POST-TENSIONED CONCRETE STRUCTURE

  • Super flat Ff numbers are possible.
  • All deck work is formed in place, requiring large resources of forming materials, shoring scaffolds and labor.
  • The location and count of post tension cable is a must.
  • Progress is much slower than other types of decks.
  • Time must be spent waiting for concrete to reach 70% of design before cables can be stressed and shoring scaffolds/ formwork can be removed for next lift.
  • If the space below the post tensioned slab is parking, a topping slab and insulation are required between conditioned space.
  • It is not as cost effective if a project only consists of one or two elevated slabs.

Cast in Place

 

3. PRECAST DECK STRUCTURE 

  • First and foremost, installation is much faster.
  • Super flat floors are possible.
  • No fireproofing is required.
  • No forming is required, except for leveling and a topping slab.
  • Larger lifting equipment is needed for the loads of precast. This requires more stable soils or mats to support the crane.
  • It is necessary to level the slab.
  • Insulation is required between the topping slab and the leveling slab when used with conditioned spaces.
  • Can require slightly larger foundations due to loads.

 

Share

Merrill Stewart is Founder and CEO of The Stewart/Perry Company, a commercial building contractor based in Birmingham.